
Introduction: When Silence Is Not an Answer
In commercial disputes involving government contracts, one of the most frustrating situations a contractor can face is the complete non-responsiveness of the other party — no acknowledgment, no reply, no appointment of an arbitrator, and no resolution in sight. This silence, often strategic, can stretch disputes over years and leave legitimate claims in a legal limbo.
A significant ruling by the Hon’ble High Court of Delhi dated November 13, 2018, in ARB.P. 446/2018, addressed precisely this situation. The case, argued by Ms. Madhumita Bhattacharjee, Advocate, resulted in the successful appointment of a former Chief Justice of a High Court as Arbitrator, along with the imposition of costs on the non-cooperative party. The ruling is a crisp but important affirmation of a contractor’s right to compel arbitration when a counterparty drags its feet.
Background: A Railway Infrastructure Contract Gone Wrong
The dispute arose from a contract for railway infrastructure works — specifically, the provisioning of Track Circuiting at multiple railway stations using Multi Section Digital Axle Counter technology, awarded by the Indian Railways in the Moradabad Division.
The petitioner, a private company specialising in rail automation, was declared the successful bidder and received a Letter of Acceptance in June 2011. The contract value was approximately ₹2.20 crores, with a stipulated execution period of nine months.
What followed was a story familiar to many infrastructure contractors dealing with government projects:
- The work could not be completed within the original timeline.
- Extensions were granted — eventually stretching to December 2014 — but crucially, without any levy of penalty, which was itself an implicit acknowledgment that the delays were not solely the contractor’s fault.
- The petitioner claimed that the delay was caused entirely by hindrances attributable to the railway authorities — site-related obstacles, coordination failures, and other impediments beyond the contractor’s control.
- By March 2015, the contractor had completed works worth approximately ₹2.18 crores out of the contracted ₹2.20 crores — a near-complete execution of the project.
Despite having substantially completed the work, the petitioner suffered losses on account of the prolonged execution period caused by these alleged hindrances. The cumulative value of the claims — including losses due to prolongation, idle resources, and other contract-related dues — exceeded ₹3 crores.
The Road to Court: Three Years of Unanswered Notices
In March 2015, the petitioner issued a formal notice to the railway authorities, doing two things simultaneously: laying out the claims it intended to pursue, and invoking the arbitration agreement contained in Clause 41 of the contract.
This notice was followed by multiple reminders over the next several years. As late as November 2017 — nearly three years after the original notice — a further reminder was sent. No substantive response was received.
With the arbitration agreement clearly triggered and the counterparty refusing to appoint an Arbitrator, the petitioner had no option but to approach the Delhi High Court under Section 11 of the Arbitration and Conciliation Act, 1996, which empowers the Court to step in and appoint an Arbitrator when a party fails to do so. The petition was filed in 2018.
The Legal Challenge: Limitation and the Respondent’s Non-Appearance
When the petition came up before the Court, the respondent’s counsel raised a preliminary objection on the ground of limitation — arguing that since the arbitration notice was issued in March 2015, the petition filed in 2018 was time-barred.
This was the central legal hurdle. The respondent, however, chose not to file a written reply despite being granted time on two separate occasions — once unconditionally, and once subject to payment of costs of ₹5,000/-. On neither occasion did the reply materialise, and ultimately the respondent’s counsel informed the Court that no reply would be filed.
The limitation objection, therefore, remained an oral submission unsupported by any pleading or documentary evidence on the Court record.
Ms. Madhumita Bhattacharjee’s Arguments: Pressing for a Decision on Merits
Appearing for the petitioner, Ms. Madhumita Bhattacharjee made a clear and effective submission: given that the matter had already lingered for a considerable period and the respondent had chosen not to file any reply, the petition deserved to be disposed of on merits without further delay.
This was a strategically sound position. By pressing for a disposal rather than allowing further adjournments, she ensured that the respondent’s deliberate silence could not be used as a tool to indefinitely stall proceedings.
She further placed on record that the cumulative value of the claims referenced in the March 2015 notice, when tallied, exceeded ₹3 crores — a figure that directly addressed the threshold conditions under the arbitration clause of the contract (Clause 41), which governed the availability of arbitration based on the proportion of the claim relative to the contract value.
This quantification was crucial: it established that the petitioner’s claims clearly met the eligibility criteria for arbitration under the contract, leaving no legitimate basis for the respondent to resist the appointment.
What the Delhi High Court Held
1. Arbitration Agreement Not in Dispute
The Court noted that the existence of the arbitration agreement in Clause 41 of the contract was not disputed by the respondents. This, combined with the fact that no written rebuttal had been filed to any of the factual assertions in the petition, left the petitioner’s case essentially uncontroverted on the Court record.
2. Claims Exceed the Threshold
The Court was satisfied that the cumulative value of the claims exceeded ₹3 crores — comfortably above the threshold contemplated in the contract’s arbitration clause — and accordingly found the petition maintainable.
3. Arbitrator Appointed
The Court appointed a Former Chief Justice of the Andhra Pradesh High Court as the Sole Arbitrator to adjudicate the disputes, with fees to be paid as per the Fourth Schedule of the Arbitration and Conciliation Act, 1996.
4. Costs Imposed
In a notable move reflecting the Court’s disapproval of the respondents’ conduct, costs of ₹7,500/- were imposed on the respondent, payable to the petitioner within four weeks. The oral limitation objection was preserved for the Arbitrator to consider during the arbitral proceedings.
Key Legal Takeaways
Section 11 Petitions Are Not Easily Defeated by Oral Objections
The respondent’s limitation argument, while raised orally, carried no weight in the absence of a written reply or supporting material on record. Courts exercising jurisdiction under Section 11 look primarily at whether an arbitration agreement exists and whether a party has failed to honour it — not at unsupported oral objections.
A Party Cannot Use Procedural Silence as a Litigation Strategy
The imposition of costs in this case sends a clear message: repeatedly seeking time to file a reply and then choosing not to do so is not a neutral act. Courts will sanction such conduct, and rightly so.
Quantifying Claims Matters at the Section 11 Stage
Ms. Bhattacharjee’s careful articulation that the claims exceeded ₹3 crores was not merely a number — it was a legal argument. It addressed the contract’s own threshold for arbitration eligibility and removed any ambiguity about whether the petitioner’s claims fell within the scope of the arbitration clause.
Government Contracts Are Not Beyond Arbitration
Despite being a contract with a government railway authority, the petitioner was able to successfully invoke arbitration. Public contracts that contain valid arbitration clauses are subject to the same arbitration regime as private contracts.
Conclusion: Persistence and Precision in Arbitration Law
This case is a practical illustration of how determined and well-prepared advocacy can overcome institutional inertia. From the initial arbitration notice in 2015 to the Court’s order in 2018, the path was neither quick nor straightforward. But by pursuing the matter methodically — issuing notices, sending reminders, filing a petition, and pressing for a decision on merits — Ms. Madhumita Bhattacharjee secured a concrete outcome for her client: a named Arbitrator, a cost award, and a preserved right to have claims adjudicated on their full merits.
For contractors working on government infrastructure projects, this case underlines the importance of documenting hindrances meticulously, invoking arbitration clauses in time, and not allowing the other party’s silence to become a substitute for justice.











